Project Managers are typically under great pressure to complete the project in as little time as possible. It is therefore imperative that project managers become familiar with the basic techniques to shorten the critical path and the many different ways to do this.
Read the post on Ten Six
Tips and considerations about project management and control using Primavera P6 and other information for application mastering.
Wednesday, November 4, 2015
To Shorten The Critical Path
Tuesday, May 26, 2015
The Negatives of Negative Lag
Are you looking for ways to fast track your schedule? Fast tracking or “crashing the schedule” can employ various methods, but typically takes activities that are scheduled in series and performs all or some of their duration in parallel to shorten the project’s planned or remaining lifecycle.
If you want to shorten your schedule by fast tracking then you most likely are considering the use of lags or negative lags, the latter otherwise known as ‘leads’.
Read the rest on Tensix Blog
Monday, April 20, 2015
Measuring Project Progress: 6 Methods You Should Know
By Reshma Sadhu
Accurately measuring the progress of a project is always a challenge. There are many factors to account for in an progress update – type of measurement, accuracy of the data, frequency of the collect and the system of record are all important factor in accurate progress measurements.
And software packages like Primavera P6 don’t always help us out. Sure there a 3 choices for Percent Complete Types, but how to we decide which one works best and under which conditions?
Inaccurate progress will foil your ability to spot early warning signs of trouble ahead, so to avoid that, here are 6 common methods for measuring project progress that will help you best measure performance and work completion. The methods below are summarized from “Project Control: Integrating Cost and Schedule in Construction,” by Wayne Del Pico.
1. Units Completed
The Units Completed lends itself well to tracking tasks that are done repeatedly, where each iteration can easily measured. Usually a task that is done repeatedly tends to take about the same amount of time, resources and effort, so tracking the units completed works well here. A simple example could be installing standard light fixtures. Each fixture takes roughly the same amount of time; if we had 100 fixtures to install then we can simply count the units installed. In this case there’s no subjective experience-based judgement involved.
2. Incremental Milestones
Also known as the ‘steps’ method, the incremental milestones method is predominantly used for cost accounts that involve subtasks that need to be completed in an orderly fashion. An example of this technique is the forming and placing of a concrete foundation wall. Laying the foundation wall on footings, erecting inside wall panels and brace, setting horizontal and vertical rebar in formwork and so forth needs to be done in sequence to complete the task appropriately.
So how do you calculate this data? The calculation is built on each single item step and the budgeted amount of time (labor hours) that is needed to complete the task by the construction crew. As each step is completed, that is documented as a mini-milestone which represents a percentage of the total installation process. The percentage given for each subtask can vary based on the project and this progress is usually agreed on to be used as a measuring took beforehand. A good way to implement this method in Primavera P6 is using Activity Steps.
3. Start/Finish
This method is only focused on capturing the starting point and the finishing point of the task and nothing in between. This method is best for tasks that are short in duration. You would implement this method if the task’s work estimations are not available or if the percent complete progress data is too difficult to collect.
“Classic examples include testing services such as load test on electric panels, flushing and cleaning of piping, and similar tasks.”1
Using the Start/Finish technique, we earn a percentage of progress when the task starts and the other half is earned once the task is complete. These percentages are determined by the owner and contractor of the project.
Often, companies agree to use the standard 50/50 Rule or other rules:
50/50 Rule – once started, the task is marked as 50% complete, and the balance is earned at final completion of the work.
20/80 Rule – used to track higher value tasks that takes a longer time to reach completion.
0/100 Rule – this rule illustrates that once 100 percent of the task is completed, only then will the value be earned. An example of this is in testing or experimental tasks since you cannot get results until the task is completed.
4. Cost Ratio
The Cost Ratio method is usually implemented on a project that has tasks that tend occur over a long phase or the entire project. Often used for Overhead costs, this technique is measured based on the budgeted allocation of dollars vs. the labour hours of production. This method gives the contractor the ability to earn value that is equal to the overall percent of project completion.
“For example,[] if the overall progress of the project was determined to be 42 percent, then the contractor would have earned 42 percent of the overhead and fees.”1
5. Experience/Opinion
Unlike the methods above that rely on definitive data, this method is relies on the experience and subjectivity of the project manager. This technique is used for tasks such as dewatering or frost removal/protection. It’s not usually recommended and tends to be seen as the last resort because each individual’s experiences and opinions vary from one another and can cause conflict between owners, contractors and architect.
6. Weighted or Equivalent Units
This method was highlighted as the best technique in the text and is the one that requires more effort, but also extends to a wider data range. The tasks that are being calculated tend to occur over a longer duration time and includes multiple subtasks, where subtasks can have different units of measurements.
The example used to illustrate this method is building a structural steel package. In order to complete this project it requires various units, labor hours, resources and subtasks. So to calculate the subtasks, it’s weighted on the estimated level of efforts in labor hours or by monetary value that is particular to each subtask. Once the weighted value is determined, it’s converted to reflect that value in units of measure specific to the task – and for this example, the units of measure would be tons. So once each subtask has been completed, the weighted tons (units of measure) is then converted to the equivalent units of percentage complete of the overall project.
These 6 methods for measuring project progress are commonly used in Construction project management and filter into a process of determining a percentage complete for the project as a whole using Earned Value Management.
Which of these methods do you the most on your projects?
Wednesday, March 25, 2015
Is Retained Logic the best Scheduling Option in Primavera?
Primavera has three Scheduling Options to choose from when you are scheduling your project. Retained Logic is the default scheduling option. When you are building a Baseline, the default option works fine. But things change when you start updating your project, activities start getting delayed and do not get executed as planned. You then have to make a decision on whether you want to continue using Retained logic or choose Progress Override or Actual Dates as your Scheduling Option. A lot has been discussed over the internet forums on which option is the best for a project and Retained Logic has won with an overwhelming majority. But I have a different opinion.
From Amit Parmar em www.theprimaverablog.com
Monday, March 9, 2015
Using Physical and Duration Percent Complete Types In Primavera P6
If you are looking for a quick way to update the progress of work on your Primavera P6 schedule or you want to describe the progress of work that has a non-uniform production rate, then you should become familiar with the different Percent Complete Types offered in Oracle Primavera P6.
Here we will start with the situation where you already have a schedule and associated baseline. There is demand for accurate, weekly updates on your project and you need an efficient and accurate way of modeling activity progress. This is where the different Percent Complete Types in Primavera P6 come in rather handy.…
See the article on the Tensix Consulting blog site.
A useful exercise would be to take the example schedule used in this article and provide weekly updates to it, comparing your results to those in this article.
Wednesday, February 25, 2015
Tracking Costs in Primavera P6
Do you know how to track schedule costs in Primavera P6? Most of us are familiar with the process of updating and tracking schedule activity progress from a time standpoint, but what about the cost of those activities? Well, Primavera P6 has features available for keeping track of the cost of labor, equipment, and material resources. It is also possible to track the cost of project specific expenses.
This article describes the process of tracking the cost of labor resources on a project. It considers a schedule where all activities are on the critical path, so a delay in any activity will result both an increased activity cost and project management cost.
See the rest of the post in Tensix Blog here
Friday, February 6, 2015
Planned dates in Primavera P6
Primavera P6 has quite a few date fields that are often misunderstood. Perhaps no date field is stranger than the “planned” date. To begin with, there will always be a Planned Start and a Planned Finish date associated with every activity. In a schedule with no progress (or what we would traditionally call the “baseline” if P6 did not use this designation for target schedules) the following is always true:
- Planned Start = Start
- Planned Finish = Finish
Once progress is recorded, however, all bets are off. The planned dates will not reflect actual dates, for example. Primavera P6 shows actual dates in the Start and Finish columns, making it easy to see which activities have progress (take that, Microsoft Project!) without having to add the Actual Start and Actual Finish columns. Space is always at a premium in a printout so not having to add the actual columns is a nice benefit.
Here is where it gets interesting. Changing the Planned Start or Planned Finish date on an activity with no progress will change the Start and Finish dates and likewise move the bar in the Gantt Chart. The rules are:
- Changing the Planned Start changes the Start date, even if the Planned Start is beforethe original Start date
- Changing the Planned Finish moves the Finish date and changes the Original Duration to match
- Changing the Planned Start and Planned Finish will move the Start and Finish dates accordingly
- No other activities are affected by changes to the Planned dates of an activity
None of this will happen, however, if the “Schedule automatically when a change affects date” scheduling option is selected. This is because scheduling the project wipes out the changes made to the Planned dates. These are not constraints, after all. The logic was never modified. Which may seem like Planned dates are a cruel trick.
Well, we create logic for a reason. Moving bars around is not scheduling. Logic is supposed to drive dates. A few constraints are okay – although some owners are adamant about having none – as long as they do not cause an interruption to the critical path. Postponing the start of a critical activity would obviously make no sense.
Thursday, January 8, 2015
Using Level of Effort (LOE) Activities in Primavera P6
Level of Effort (LOE) activities are typically used to define effort that in and of itself doesn’t generate a deliverable, but does incur labor/costs to the project. Items such as management, security or safety are ongoing and require resources but are not on the critical path. These overhead costs are usually not immaterial. Overhead efforts can span part of the project, or the entire life-cycle. They are also associated with other activities in the project.Modeling these efforts and cost individually by assigning resources to every activity is prohibitive. So how does one easily define the effort of these tasks throughout the life-cycle of the project? Well, Primavera P6 has a Level of Effort activity type to help you model this type of work in a low-maintenance way, and one that does not interfere with the critical path.
Read More in TenSix