Project schedules tend toward tardiness, but what can be done to make schedules more reliably on time? Schedule buffer similar to a cost contingency helps projects become more reliable.
Tips and considerations about project management and control using Primavera P6 and other information for application mastering.
Wednesday, January 31, 2018
Schedule Reliability and Buffers
Wednesday, December 27, 2017
Spending Plan
“Spending Plan” is the least used option in Primavera, but it is especially helpful when you want to track your Actual Costs against the Budget allocated to your project. You can track Actual Cost vs. Budget across WBS and rolling up to your Project and ultimately to your EPS. While using Spending Plan we need to keep one this in mind that this method uses a Top Down approach i.e. You have a total budget on the top node (Project) and you distribute it to the respective EPS/WBS underneath it.
|
WBS
|
Spending Plan
|
Spending Plan Tally
|
|||
|
WBS 1
|
200
|
200
|
Rolls up from WBS 1.1 + 1.2
|
||
|
WBS 1.1
|
100
|
0
|
No Spending
Plan Tally cause no child node
|
||
|
WBS
1.2
|
50
|
0
|
No Spending
Plan Tally cause no child node
|
||
|
WBS 2
|
50
|
10
|
Rolls up from WBS 2.1
|
||
|
WBS 2.1
|
10
|
0
|
No Spending
Plan Tally cause no child node
|
||
|
WBS
|
Spending Plan
|
Spending Plan Tally
|
Undistributed Current Variance
|
|
WBS 1
|
200
|
200
|
0
|
|
WBS 1.1
|
100
|
0
|
100
|
|
WBS 1.2
|
50
|
0
|
50
|
|
WBS 2
|
50
|
10
|
40
|
|
WBS 2.1
|
10
|
0
|
10
|
Monday, December 11, 2017
Assigning Fixed Price Costs to Activities in Primavera P6
Primavera P6 has a standard process for creating and assigning labor, material, and equipment resources to compute activity cost. What if the activity is performed at a fixed price? Yes, there is a way to specify a fixed price activity cost in Primavera P6 Professional.
Tuesday, December 5, 2017
What is a Project Plan?
In large enterprises with hundreds or thousands of capital projects, it is important to create standards to which all projects must adhere. This provides the organization the ability to roll up and assess overall project performance across the organization as well as look at resource capacity and other key performance indicators.
Read the post on Ten Six
Thursday, October 27, 2016
Is Retained Logic the best Scheduling Option in Primavera?
Has your project ever followed the exact logic that you planned in your baseline?
- Retained Logic
- Progress Override
- Actual Dates
Retained Logic- Retains the logic of your relationships while scheduling the project
Progress Override – Assumes that relationship logic can be ignored for out-of-sequence activities
Actual Dates – Uses the Actual Dates of the activity for Forward Pass and Backward Pass calculations
Tuesday, September 20, 2016
Why Project Calendars Are Preferable to Global Calendars
Summary
reproduced from Tensix
Wednesday, July 27, 2016
Conscientious use of constrains
Wednesday, June 8, 2016
The Case Against “Must Finish By”
Read the article on...
Friday, May 13, 2016
Creating a Believable Schedule
Read the article on Ten Six
Tuesday, February 23, 2016
Process Control & Schedule Hierarchy
Level I: Milestone Summary Schedule
Level II: Summary Schedule
Level III: Detailed Engineering, Procurement and Construction Schedule
Level IV: Identification of detailed work plan, log list
Schedule Baseline Process
Thursday, February 18, 2016
Creating a WBS for Success
Thursday, February 4, 2016
“How Do You Know When to Use a Constraint or Lag?”
QUESTION
ANSWER
CONSTRAINTS
Overview of Constraints:
- Constraints are used to set dates in the schedule that must be met.
- Constraints directly affect the activity they are set to, and then indirectly affect the predecessor and successor activities.
- Use constraints on milestone activities to meet deadlines.
- Constraints Lare “rules” that cannot be changed.
- Do not assign too many constraints, or network logic can be ignored.
Overview of Lags:
- Lags are used to set delays or lead time between two activities.
- Lags affect the relationship between two activities (predecessor and successor).
- Apply lags to any activity type, but usually task dependent or resource dependent.
- Lags are calculated using the predecessor’s calendar.
- Lags are used when an internal force causes an activity to be delayed.
- Lags are more “controllable” within the schedule.
CONCLUSION
Wednesday, November 4, 2015
To Shorten The Critical Path
Project Managers are typically under great pressure to complete the project in as little time as possible. It is therefore imperative that project managers become familiar with the basic techniques to shorten the critical path and the many different ways to do this.
Read the post on Ten Six
Tuesday, May 26, 2015
The Negatives of Negative Lag
Are you looking for ways to fast track your schedule? Fast tracking or “crashing the schedule” can employ various methods, but typically takes activities that are scheduled in series and performs all or some of their duration in parallel to shorten the project’s planned or remaining lifecycle.
If you want to shorten your schedule by fast tracking then you most likely are considering the use of lags or negative lags, the latter otherwise known as ‘leads’.
Read the rest on Tensix Blog
Monday, March 9, 2015
Using Physical and Duration Percent Complete Types In Primavera P6
If you are looking for a quick way to update the progress of work on your Primavera P6 schedule or you want to describe the progress of work that has a non-uniform production rate, then you should become familiar with the different Percent Complete Types offered in Oracle Primavera P6.
Here we will start with the situation where you already have a schedule and associated baseline. There is demand for accurate, weekly updates on your project and you need an efficient and accurate way of modeling activity progress. This is where the different Percent Complete Types in Primavera P6 come in rather handy.…
See the article on the Tensix Consulting blog site.
A useful exercise would be to take the example schedule used in this article and provide weekly updates to it, comparing your results to those in this article.
Wednesday, February 25, 2015
Tracking Costs in Primavera P6
Do you know how to track schedule costs in Primavera P6? Most of us are familiar with the process of updating and tracking schedule activity progress from a time standpoint, but what about the cost of those activities? Well, Primavera P6 has features available for keeping track of the cost of labor, equipment, and material resources. It is also possible to track the cost of project specific expenses.
This article describes the process of tracking the cost of labor resources on a project. It considers a schedule where all activities are on the critical path, so a delay in any activity will result both an increased activity cost and project management cost.
See the rest of the post in Tensix Blog here
Thursday, January 8, 2015
Using Level of Effort (LOE) Activities in Primavera P6
Level of Effort (LOE) activities are typically used to define effort that in and of itself doesn’t generate a deliverable, but does incur labor/costs to the project. Items such as management, security or safety are ongoing and require resources but are not on the critical path. These overhead costs are usually not immaterial. Overhead efforts can span part of the project, or the entire life-cycle. They are also associated with other activities in the project.Modeling these efforts and cost individually by assigning resources to every activity is prohibitive. So how does one easily define the effort of these tasks throughout the life-cycle of the project? Well, Primavera P6 has a Level of Effort activity type to help you model this type of work in a low-maintenance way, and one that does not interfere with the critical path.
Read More in TenSix
Friday, December 26, 2014
Applying Hard Constraints to a Schedule in Primavera P6
When do you apply hard or soft constraints in Primavera P6? This is a question I had recently while working with a client and while there are no hard and fast rules as project specific circumstances can differ, here are some guidelines that may help. Many times the project schedule is influenced by certain constraints on the project. These constraints can be contractual, external, or internal.
Tuesday, December 23, 2014
BIM Implementation and Project Controls
As current regulations require BIM implementation for every public sector construction and infrastructure project from 2016 onwards[1]designers, contractors and supply chains in the industry wil l need to move on fast from their current ways of working and adapt to achieve compliance with the upcoming legislation. The policy is however, not a punitive one for the industry. It is a progressive plan to significantly improve industry efficiency, from the project management stage in design and construction to the subsequent operational management of the asset during its lifetime.
What is BIM?
Wednesday, September 3, 2014
Level of Effort Activities
I’m including three tutorials over the use of Level of Effort Activities on Primavera P6.
Setting Up LOEs and Resource Loading Them
Use of Level of Effort (LOE) activities to resource load a schedule.
Level of Effort and Percent Complete
Used primarily to resource-load an ongoing support activity in Primavera P6 schedule.
Use A Level Of Effort To Add Work Stoppage Info To A Project and Still Track To Your Primavera Baseline
When we develop a schedule we assume that an activity can be finished uninterrupted once it has commenced. But, sometime events occur which force the work on the activity to stop.
Be proactive.











