Wednesday, December 27, 2017

Spending Plan

“Spending Plan” is the least used option in Primavera, but it is especially helpful when you want to track your Actual Costs against the Budget allocated to your project. You can track Actual Cost vs. Budget across WBS and rolling up to your Project and ultimately to your EPS. While using Spending Plan we need to keep one this in mind that this method uses a Top Down approach i.e. You have a total budget on the top node (Project) and you distribute it to the respective EPS/WBS underneath it.
Note – Spending plan dates start from PS-3 Months and finishes by after 4 yrs.
The following fields are used in Spending Plan;
1) Spending Plan – This is a user entered field where you enter the allocated Budget for the WBS/Project/EPS.
2) Spending Plan Tally – is a summary and it rolls up from the child nodes. If you are using it for a project then it will rolls up one level up from the child WBS and the same for EPS nodes.
WBS
Spending Plan
Spending Plan Tally
WBS 1
200
200
Rolls up from WBS 1.1 + 1.2
WBS 1.1
100
0
No Spending Plan Tally cause no child node
WBS 1.2
50
0
No Spending Plan Tally cause no child node
WBS 2
50
10
Rolls up from WBS 2.1
WBS 2.1
10
0
No Spending Plan Tally cause no child node
3) Undistributed Current Variance – (Spending Plan – Spending Plan Tally) – Follows a Top Down logic, it shows whether you have distributed your budget to the child nodes (WBS/EPS) or not.
WBS
Spending Plan
Spending Plan Tally
Undistributed Current Variance
WBS 1
200
200
0
    WBS 1.1
100
0
100
    WBS 1.2
50
0
50
WBS 2
50
10
40
    WBS 2.1
10
0
10
4) Benefit Plan – Benefit plan follows the same logic as spending plan but indicates the benefits that you stand to gain every month. This is also a user entered field and data has to be manually entered
5) Benefit Plan Tally – Same idea as Spending Plan Tally but only for Benefits.

6) Benefit Variance – (Benefit Plan Tally value – Benefit Plan value) – Follows the same logic as Undistributed Current Variance

Monday, December 11, 2017

Assigning Fixed Price Costs to Activities in Primavera P6

Primavera P6 has a standard process for creating and assigning labor, material, and equipment resources to compute activity cost. What if the activity is performed at a fixed price? Yes, there is a way to specify a fixed price activity cost in Primavera P6 Professional.

A popular procurement contract type is the fixed price contract. In this type of agreement the subcontractor agrees to perform an activity at a fixed price, regardless, of the actual labor, material, and/or equipment costs. In this way your company procurement department transfers the risk of exceeding the budget onto the subcontractor. Any unforeseen activity expenses must be paid by the subcontractor. Great! Well, how do we specify a fixed price activity cost in Primavera P6?

Thursday, November 9, 2017

Primavera P6 and Material Resources

In Primavera P6 Professional it is possible to define labor, equipment, and material resources. Material resources require definition of a unit of measure.
Labor resources may be trade skills or specific individuals. Typically, the trade skill is inserted as a place holder until the resource manager assigns an individual to perform the work. It is important to specify the labor hourly pay rate and maximum units/time. The labor maximum units/time is how many trade specific individuals are available to work on the project. Equipment resources have a standard rate.

read on Ten Six

Wednesday, January 18, 2017

Assigning Expenses in Primavera P6 | Ten Six Consulting

f you are looking for ways to assign costs to activities in Oracle Primavera P6 without creating a global resource for every item, then you may find the Expenses feature useful. A project expense can be many things: administration, travel, consulting, software, facilities, training, you name it. The Expenses tool is also ideal for project-specific material items, such as custom built items that need to be identified in the schedule, but again, don’t really belong in the resource pool.


Assigning Expenses in Primavera P6 | Ten Six Consulting:



'via Blog this'

Thursday, June 2, 2016

Assigning Fixed Price Costs to Activities in Primavera P6

Primavera P6 has a standard process for creating and assigning labor, material, and equipment resources to compute activity cost. What if the activity is performed at a fixed price? Yes, there is a way to specify a fixed price activity cost in Primavera P6 Professional.

A popular procurement contract type is the fixed price contract. In this type of agreement the subcontractor agrees to perform an activity at a fixed price, regardless, of the actual labor, material, and/or equipment costs. 


Read the post on TenSix

Wednesday, November 4, 2015

To Shorten The Critical Path

Project Managers are typically under great pressure to complete the project in as little time as possible. It is therefore imperative that project managers become familiar with the basic techniques to shorten the critical path and the many different ways to do this.

Read the post on Ten Six

Wednesday, February 25, 2015

Tracking Costs in Primavera P6

Do you know how to track schedule costs in Primavera P6? Most of us are familiar with the process of updating and tracking schedule activity progress from a time standpoint, but what about the cost of those activities? Well, Primavera P6 has features available for keeping track of the cost of labor, equipment, and material resources. It is also possible to track the cost of project specific expenses.

This article describes the process of tracking the cost of labor resources on a project. It considers a schedule where all activities are on the critical path, so a delay in any activity will result both an increased activity cost and project management cost.

See the rest of the post in Tensix Blog here

Thursday, January 8, 2015

Using Level of Effort (LOE) Activities in Primavera P6

Level of Effort (LOE) activities are typically used to define effort that in and of itself doesn’t generate a deliverable, but does incur labor/costs to the project. Items such as management, security or safety are ongoing and require resources but are not on the critical path. These overhead costs are usually not immaterial. Overhead efforts can span part of the project, or the entire life-cycle. They are also associated with other activities in the project.
Modeling these efforts and cost individually by assigning resources to every activity is prohibitive. So how does one easily define the effort of these tasks throughout the life-cycle of the project? Well, Primavera P6 has a Level of Effort activity type to help you model this type of work in a low-maintenance way, and one that does not interfere with the critical path.
Read More in TenSix

Monday, September 15, 2014

Export Resources without Cost Data

The purpose of exporting Primavera P6 files in “XER” format is to transmit all of the project data to another database. In many cases we are not looking to exclude any data. So how do we avoid sharing sensitive cost data with other parties? Contractors may not want owners, subcontractors and other parties to have access to this proprietary information.

There are two options for not sharing cost data. One option is to delete resource assignments altogether. We do this by copying the schedule inside Primavera P6 and un-checking the “Resource & Role Assignments box, as seen below:

clip_image001

While this option works perfectly well, the recipient will see no resources or roles in the schedule. What if we want the recipient of this file to be able to see the resource units but not the unit prices? This requires a different approach. Option 2 involves creating a new user and associated user profile who is not allowed to view cost data. When this user exports the file the resource rates will disappear but the resource assignments and units will remain intact.

First, we create a new user and label that person in such a way that we remember why this user was created in the first place. Go to Admin → Users. Below, I have added a new user with the name “Export User”:

clip_image002

Note that I have given this new user access to every project in my database by assigning this user to the highest level in the Organization Breakdown Structure (OBS). This is not absolutely necessary but it does make it easier to export any project without cost data.

Second, we need to assign the new user a Project Profile that excludes the ability to “View Project Costs/Financials”. Go to Admin → Security Profiles and select Project Profiles. In the screenshot below I have added a new Project Profile, “No Costs Exported”:

clip_image003

Also, I gave this new user no ability to modify schedules because the only purpose of this user is to export projects sans cost data. As soon as the project has been exported I will log back in using my normal user name.

Now we are ready to export a project with cost data. Keep in mind that you will need to log in as the new user first!

From Bill Peppon