Tips and considerations about project management and control using Primavera P6 and other information for application mastering.
Monday, February 15, 2016
Cannot filter on Start or Finish date
Wednesday, February 10, 2016
How to get the Values of Your Activity Codes to Customize the Look of Your Gantt Chart in Primavera P6?
P6 Activity Codes as a Source of Gantt Bar Configuration
This is a very simple example. Be creative and use the functionality of the Bar Configurations to help you with creating the customized Gantt Bar(s) you require. With the bar configurations you need enabled – save your layout – create different layouts/bar configurations as required.
Monday, February 8, 2016
Things You Should Know About Primavera P6 Calendars
1 – Calendars are assigned to activities, not projects
Thursday, February 4, 2016
“How Do You Know When to Use a Constraint or Lag?”
QUESTION
ANSWER
CONSTRAINTS
Overview of Constraints:
- Constraints are used to set dates in the schedule that must be met.
- Constraints directly affect the activity they are set to, and then indirectly affect the predecessor and successor activities.
- Use constraints on milestone activities to meet deadlines.
- Constraints Lare “rules” that cannot be changed.
- Do not assign too many constraints, or network logic can be ignored.
Overview of Lags:
- Lags are used to set delays or lead time between two activities.
- Lags affect the relationship between two activities (predecessor and successor).
- Apply lags to any activity type, but usually task dependent or resource dependent.
- Lags are calculated using the predecessor’s calendar.
- Lags are used when an internal force causes an activity to be delayed.
- Lags are more “controllable” within the schedule.
CONCLUSION
Monday, February 1, 2016
Primavera Functions That Project Managers Must Know
Wednesday, November 4, 2015
To Shorten The Critical Path
Project Managers are typically under great pressure to complete the project in as little time as possible. It is therefore imperative that project managers become familiar with the basic techniques to shorten the critical path and the many different ways to do this.
Read the post on Ten Six
Tuesday, May 26, 2015
The Negatives of Negative Lag
Are you looking for ways to fast track your schedule? Fast tracking or “crashing the schedule” can employ various methods, but typically takes activities that are scheduled in series and performs all or some of their duration in parallel to shorten the project’s planned or remaining lifecycle.
If you want to shorten your schedule by fast tracking then you most likely are considering the use of lags or negative lags, the latter otherwise known as ‘leads’.
Read the rest on Tensix Blog











