A Schedule
Hierarchy defines the schedule control system and several interrelated levels
of schedules at various levels. Schedule hierarchy provides a framework for
project schedule development.
Primarily,
there are following 4 level of schedules being applied on medium to large size
projects to identify the scope and division and as well as contractual/project
milestones.
Level I: Milestone Summary Schedule
Depicts
overall time frame of project, covers total project scope and highlights
contractual and Project milestones. This schedule is used by Management to
highlight major and significant events as well as to communicate overall scope
and status of project. This level schedule can also be used for decision
making.
Level II: Summary Schedule
Level II
Schedule is summarized by facility, discipline and areas for Engineering,
highlighting long lead items, critical items for Procurement, and summarized by
work package for Construction. Level II schedule establish requirements at the
facility level, phase or work phase. It depicts the relationship between
facilities/phases and establish facility criticality.
Level III: Detailed Engineering, Procurement and Construction Schedule
Integrated
EPC Schedule where Engineering is sorted by discipline, grouped by systems/area
depicting system requirement. Procurement identifies demand by facility/area or
systems and as well identify the major equipment delivery. Construction/startup
is grouped by system/area depicting interrelationships and timeframes. Level
III Schedules establish the basis for staff requirements Task deliverables,
material and subcontract requirements and bull release and installation rates.
Level III schedule establish construction equipment requirements and integrates
facility/area breakdown into system turnover packages. Level III schedules are
maintained at regular basis and used for What-if analysis.
Level IV: Identification of detailed work plan, log list
Level IV schedule is broken down at work
activity level i.e., drawings, specs, data sheets etc. It depicts construction
by work package/area/facility/craft/crew and establish construction sequence.
Level IV schedule provides basis for detail construction work planning and
rolling schedules and its a working document that is continually updated and
revised to reflect project needs and circumstances.
Schedule Baseline Process
Schedule
must be baselined to map it to current schedule to avoid slipages and to get
early warnings. This also assists in developing planned S Curves and histograms
to keep the current schedule on track.
No comments:
Post a Comment