The Case Against “Must Finish By”

When setting up a new project, the user will be faced with the “Must Finish By” option. Our advice is to leave it blank. Yes, every project has a finish date. Otherwise, it does not meet the definition of a project. That is to say, a project must be: (1) unique, (2) have a specified time frame, and (3) a defined scope of work. Unfortunately, projects often end up with a longer time frame and increased scope, but that is a subject for another day.
To review, the “Must Finish By” constraint is presented... 