How To Find Relationship Lag in Primavera P6

How To Find Relationship Lag in Primavera P6:

....
According to the Practice Standard for Scheduling, a document prepared by scheduling experts at the Project Management Institute, using Relationship leads or lags add significant schedule risk to a project.    The main reason is the lack of visibility of lag delays on project schedules.  Lag time is hard to identify and document – it isn’t obvious when looking at the Gantt Chart or when analyzing a schedule’s dates.   When lag time is used on a schedule, it is very rarely documented why the delay was added,  causing construction managers to scratch their heads.  ....